Media
Statement
For immediate
release
UNRULY INDIVIDUALS
PREVENT LEP CONTRACTORS FROM ENTERING SCHOOL
Syarikat Prasarana Negara Berhad (Prasarana) expresses its frustration that efforts
by its contractors to enter and start construction works at SRJK Tamil
Castlefield today was prevented by a group of unruly individuals, despite the
company obtaining the court injunction and other relevant approvals from the authorities.
The unruly individuals
brusquely removed the barricades put up by the contractors to demarcate the
work area.
The individuals also had a
number of scuffles with the auxiliary policemen from Prasarana, resulting in a
senior officer being injured in the arm.
“We are extremely
disappointed that our efforts to build the LRT Line Extension Project (LEP)
have been hindered by the reckless actions of these individuals despite us
obtaining the court injunction to enter part of the school compound and
informing the school authorities ahead of our plan.
“This is the third time that
we have made the effort to enter the site and we have stated repeatedly that we
will ensure minimum interruption to the children’s studies while construction
of the LEP is underway,” said Prasarana’s Group Director of Project Development
Division, Encik Zulkifli Md Yusoff.
In fact, Prasarana has
committed to build sound-proof barriers, improve the school’s facilities which
include installing air-conditioning units at classrooms as well as improve the
landscaping by planting more trees and foliage as a gesture of goodwill towards
enhancing the comfort and convenience of the school children and teachers of
the school.
“We are dedicated towards
ensuring that the well-being of the school children and their teachers are not
compromised during this period. Apart from enhancing the school’s facilities,
we will employ measures to ensure safety of the school children and the public in
our construction methods and practices. This will involve setting up secured
and proper hoarding and safeguarding the project area, traffic management plans
as well as safety notices for the public’s understanding and awareness,” Encik
Zulkifli added.
As a matter of fact, in the
past, there are several LRT alignments that has been built nearby schools such
as :
- Sekolah Methodist
Wesley, Sentul, KL
- SRJK (T) Appar, Jalan
Merpati, KL
- SRJK (C) Chong Kwok,
Jalan Merpati, KL
- SK (L) Jalan Batu, KL
During construction, the LRT
Project contractors will only occupy 0.47 acres out of 2.8 acres of the school
compound and upon completion of the construction; the five LRT piers will only occupy
20m2 of of the space. The construction
of the five piers will take about 12 months to complete, barring no further
disruptions in the process.
The 17.7km extension of the
Ampang LRT Line, which runs from the current Sri Petaling LRT Station to the
integrated Putra Heights stations, involved a 180-meter stretch that passes the
edge of the SRK Tamil Castlefield school field; running parallel to the
Lebuhraya Puchong Damansara (LDP) and the construction of five pillars
Pejabat Tanah dan Daerah
Petaling has given the approval to Prasarana in January 2011 to enter
government land within the LRT alignment and to start the construction works.
Progress of the LRT Project
has been hampered by increasing demands from SRK Tamil Castlefield’s School
Board. This culminated in a stalemate in the negotiation process as they would
only allow entry for the LRT Project contractors if they are given a new piece
of land to relocate the school plus other incentives. That sparked a series of
meetings with various agencies including the state’s economic action unit
(MTES), Education Ministry, Transport Ministry and the local authorities.
Ministry of Education has set
a requirement that 100 percent approval from all parents must be obtained for
the relocation.
On 21 November 2013, a group
of 80 parents came out in the open to voice their disagreement for the
relocation exercise; signing a document to state their position and voicing out
their concerns for the delay of the LRT Project.
While these meetings
continued, the School Board remained adamant that no work should start at the
site; forcing Prasarana and its contractors into endless wait while incurring
needless expenses.
Encik Zulkifli said “It is
important for the public to understand that the LEP can coexist with SRK Tamil
Castlefield harmoniously and there is no need for the school to be relocated in
order for this project to commence. There are many benefits to consider, key of
which is improved transport convenience for the students and surrounding
residents to the greater LRT network in Klang Valley once it has been
completed. The LEP will alleviate
traffic congestion as well as provide quick and efficient way for them to
travel to work, public areas and schools.”
Implemented under the
National Key Result Area (NKRA), the LEP project involves extension of both the
existing LRT lines – Ampang Line and the Kelana Jaya Line.
For the Ampang Line, which
would directly benefit residents in Petaling, Bandar Kinrara, Puchong and Putra
Heights, the current LRT line is extended to Putra Heights integrated station.
Also with Putra Heights as
the last station, the Kelana Jaya Line would be extended from the current
Kelana Jaya LRT station; passing through Lembah Subang, Subang Jaya, USJ and
Subang Alam near Shah Alam.
Ends
No comments:
Post a Comment